PMP Sample Questions
PMP is nothing but Project Management Professional. PMP Certification is offered by the Project Management Institute (PMI).
The PMP sample questions are based on the following objectives:
- Project Initiating
- Project Planning
- Project Executing
- Project Controlling
- Project Closing
- Professional Responsibility
Some PMP sample questions are given below:
- Regarding management and leadership all of the following are true except
- On a project, particularly a larger project, the project manager is generally expected to be the project's leader as well.
- Technical leadership is of primary importance in project management
- Managing is primarily concerned with consistently producing key results expected by stakeholders
- Leading involves establishing direction, aligning people, motivating and inspiring
Answer: B
- A company has to make a choice between two projects, because the available resources in money and kind are not sufficient to run both at the same time.Each project would take 9 months and would cost $250,000.
- The first project is a process optimization which would result in a cost reduction of $120,000 per year.This benefit would be achieved immediately after the end of the project.
- The second project would be the development of a new product which could produce the following net profits after the end of the project:
| 1 |
year: |
$ 15,000 |
| 2 |
year: |
$ 125,000 |
| 3 |
year: |
$ 220,000 |
Assumed is a discount rate of 5 % per year.Looking at the present values of these projects' revenues in the first 3 years, what is true?
- Both projects are equally attractive.
- The first project is more attractive by app.7%.
- The second project is more attractive by app.5%.
- The first project is more attractive by app.3%.
Answer: D
- A production process has been defined as part of an industrial equipment manufacturing project.The process is intended to produce steel bolts with a length of 20 cm.The acceptable control limits are 19.955 cm and 20.045 cm.
The measurements made at the end of the process yielded the following results:
20.033 cm, 19.982 cm, 19,995 cm, 20.006 cm, 19.970 cm, 19.968 cm, 19.963 cm,
19.958 cm, 19.962 cm, 19.979 cm, 19.959 cm.
What should be done?
- The process is under control.It should not be adjusted.
- The process should be adjusted.
- The control limits should be adjusted.
- The measuring equipment should be recalibrated.
Answer: B
- What are the 4 stages of team development?
- Forming, Storming, Norming, Performing.
- Enthusiasm, Hope, Panic, Solution.
- Assignment, Kickoff, Training, Communicating.
- Direction, Motivation, Cooperation, Collaboration.
Answer: A
- During a software project Earned Value Analysis is performed and gives the following results:
EV: 523,000; PV: 623,000; AC: 643,000.
Which results are correct?
- CV: +120,000; SV: +100,000.
- CV: +100,000; SV: +120,000.
- CV: -100,000; SV: -120,000
- CV: -120,000; SV: -100,000.
Answer: D
- Which of the following is not normally an element of the Project Charter?
- The formal authorization to apply organizational resources to project activities.
- Work package descriptions.
- The business need that the project was undertaken to address.
- The product description or a reference to this document
Answer: B
- Which process is applied to break down the project into smaller, more manageable elements?
- Scope Planning.
- Activity Duration Estimating.
- Scope Definition.
- Scope Verification.
Answer: C
- Which of the following Tools and Techniques are part of Risk Management Planning?
- Risk planning meetings.
- Documentation reviews.
- Data precision rankings.
- Diagramming techniques.
Answer: A
- All of the following statements concerning project stakeholders are true except
- Differences between or among stakeholders should be resolved in favor of the customer.
- Managing stakeholder expectations may be difficult because stakeholders often have very different objectives, that may come into conflict.
- Project stakeholders may influence the course of the project and its results.
- Differences between or among stakeholders should be resolved in the most cost efficient manner consistent with project objectives.
Answer: D
- Which of the following is the output of Source Selection?
- Proposals.
- Evaluation criteria.
- Contract negotiation.
- Contract.
Answer: D
Next »
PMP Sample Question Number :
1-10|
11-20|
21-30|
31-40|
41-50|
51-60|
61-70|
71-80|
81-90|
91-100|
101-110|
111-120|
121-130|
131-140|
141-150|
151-160
|