  1. A narrative description of products or services to be supplied under contract is called:

    • the project plan.
    • a statement of work.
    • an exception report.
    • Pareto analysis.

    Answer: B

  2. An example of scope verification is:

    • reviewing the performance of an installed software module.
    • managing changes to the project schedule.
    • decomposing the WBS to a work package level.
    • performing a benefit/cost analysis to determine if we should proceed with the project.

    Answer: A

  3. Which of the following is not an example of a source of scope change?

    • a variation in government regulations.
    • failure to include a required feature in the design of a telecommunication system.
    • a need to engage in bottom-up cost estimating.
    • introducing technology that was not available when scope was originally defined.

    Answer: C

  4. The subdivision of major project deliverables, as identified in the scope statement, into smaller, more manageable components is called:

    • parametric estimation.
    • scope definition.
    • feasibility analysis.
    • benefit-cost analysis.

    Answer: B

  5. The process of establishing clear and achievable objectives, measuring their achievement, and adjusting performance in accordance with the results of the measurement is called:

    • strategic planning.
    • alternative objectives inventory.
    • management by objectives.
    • contingency planning.

    Answer: C

  6. Configuration management is:

    • used to ensure that the description of the project product is correct and complete.
    • the creation of the work breakdown structure.
    • the set of procedures developed to assure that project design criteria are met.
    • a mechanism to track budget and schedule variances.

    Answer: A

  7. A fundamental tenet of modern quality management holds that quality is most likely to be achieved by:

    • planning it into the project.
    • developing careful mechanisms to inspect for quality.
    • striving to do the best job possible.
    • conducting quality circle activities.

    Answer: A

  8. Your most recent project status report contains the following information: BCWP = 3,000, ACWP = 3,500, and BCWS = 4,000. The schedule variance is:

    • + 1,000.
    • + 500.
    • - 500.
    • - 1,000.

    Answer: D

  9. Learning curve theory emphasizes that in producing many goods:

    • cost decreases as production rates increase.
    • average unit cost decreases as more units are produced.
    • materials become cheaper when they are purchased in bulk.
    • laborers become more productive because of technological advances.

    Answer: B

  10. Rearranging resources so that constant resource levels are maintained is called:

    • floating.
    • leveling.
    • restructuring.
    • crashing.

    Answer: B

« Previous || Next »

PMP Sample Question Number : 1-10| 11-20| 21-30| 31-40| 41-50| 51-60| 61-70| 71-80| 81-90| 91-100| 101-110| 111-120| 121-130| 131-140| 141-150| 151-160


© All Rights Reserved, indicareer.com | partners

IIT JEE | Jobs in India | Sample Resume | Resume Writing | Sample Letters
Site optimized by SEO India company.