PMP Sample Questions
- Which of the following are not cost of quality?
- Prevention costs.
- Failure costs.
- Transportation costs.
- Appraisal costs.
Answer: c
- What is a trigger in project risk management?
- An expected situation causing an unidentified risk event to occur.
- A warning sign that an identified risk event might have occurred.
- An unexpected situation causing an identified risk event to occur.
- An unexpected situation causing an unidentified risk event to occur.
Answer: b
- According to the project plan, a contractor is scheduled to deliver some software components at the end of the day. A regular payment is due to be made to this contractor tomorrow.
The project team received a note this morning informing them that the software delivery will be delayed by 2 weeks.
This morning, the project team received a note that the software will be delayed by 2 weeks.
How should the project management team react?
- The project management team should delay payment for 2 weeks.
- The project management team must immediately find a different contractor.
- The project management team should conduct a meeting with the contractor to resolve the delivery issues before making the payment.
- The project management team should make the payment and reschedule the project plan.
Answer: C
- In a software company a large number of simultaneously performed projects utilize the same groups of human and other resources.
What is the term commonly used for this situation?
- Concurrent engineering.
- Resource over-allocation.
- Resource pooling.
- Program management
Answer: c
- What does the acronym RAM commonly stand for in project management?
- Responsibility Assignment Matrix.
- Remotely Applied Measurements.
- Risk Aware Management.
- Randomly Accessible Material.
Answer: A
- What is not handled as a constraint in project management?
- Laws and regulations.
- Limits of authorization.
- Team preferences.
- Physical constraints.
Answer: C
- A precontract agreement that establishes the intent of a party to buy products or services is called a
- Seller initial response.
- Seller immediate response.
- Letter of intent.
- Letter of credit.
Answer: C
- What should not be part of a risk management plan?
- Roles and responsibilities for handling risks.
- Timing of risk management activities.
- The managerial approach towards risk.
- Individual risks
Answer: D
- A project manager performs Earned Value Analysis and finds the following results:
EV: 250,000; PV: 200,000; AC 275,000
BAC is 500,000.
What is right?
- EAC = 400,000
- EAC = 550,000
- BTC = 400,000
- ETC = 75,000.
Answer: B
- The construction of a residential home will cost a certain amount per square foot of living space. This is an example of what type of estimating?
- Analogous estimating.
- Bottom-up estimating.
- Top-down estimating.
- Parametric modeling.
Answer: D
« Previous || Next »
PMP Sample Question Number :
1-10|
11-20|
21-30|
31-40|
41-50|
51-60|
61-70|
71-80|
81-90|
91-100|
101-110|
111-120|
121-130|
131-140|
141-150|
151-160
|