PMP Sample Questions
- Activity 1 has a duration of 20 days, Activity 2 of 10 days, Activity 3 of 5 days and Activity 4 of 6 days. What is the minimum total duration between the Milestones A and B?

- 36 days
- 37 days
- 39 days
- 42 days
Answer: B
- Which of the following statements is true concerning Scope Definition?
- The Activity List is a principle output used for resource allocation and is an input to network diagramming.
- The Scope Statement is a principle output containing a narrative description of project work and deliverables.
- The Project Charter is a principle output and authorizes the project.
- The Work Breakdown Structure is a principle output and should be broken down to a level which allows sufficient accuracy in planning.
Answer: D
- All the following statements regarding "whistleblowing" are true except
- It is the term used to define an employee’s decision to disclose information on unethical, immoral or illegal actions at work to an authority figure.
- An employee should always discuss the matter with people external to the company before following the "chain of command" and discuss it with the immediate superior.
- The consequences of whistleblowing are often extreme and include possible being branded as having bad judgment, firing, civil action and imprisonment.
- Carefully considered whistleblowing can lead to the end of unethical business practices.
Answer: B
- Which of the following statements is not true?
- Attribute sampling is the process of assessing whether results conform to specifications or not.
- Prevention means keeping errors out of the process
- Variables sampling means that the result is classified into one of the 3 categories:
"acceptable" - "acceptable after rework" - "rejected".
- Inspection means keeping errors out of the hands of the customer.
Answer: C
- Why should assumptions be documented?
- Assumptions might prove to be wrong. Knowing which assumptions were incorrect allows baseline adjustments in case of project crisis.
- Assumption analysis is a valuable tool and technique of Risk Identification.
- Assumptions limit the project management team's options for decision making.
- In case of schedule or budget overruns, the documentation of assumptions supports a clear assignment of responsibility.
Answer: B
- All the following statements are true except
- It is axiomatic of the quality management discipline that the benefits outweigh the costs.
- Quality should be tested and inspected into work results on a regular base.
- The primary cost of meeting quality requirements is the expense associated with project quality management activities.
- The primary benefit of meeting quality requirements is less rework, which means higher productivity, lower costs, and increased stakeholder satisfaction.
Answer: B
- Which of the following statements about diagramming methods is not
- PDM is the same as AON.
- ADM is the same as AOA.
- GERT is the same as System Dynamics Model.
- GERT and System Dynamic Model are examples of conditional diagramming methods
Answer: C
- A project is managed by a project coordinator. Which of the following statements is most likely to be true?
- The performing organization is a weak matrix.
- The performing organization is doing "management by projects".
- The performing organization is a strong matrix.
- The performing organization is projectized.
Answer: A
- Which of the following statements concerning cross-cultural differences is true?
- There is no one "best way" for project organization.
- Some cultures have values, some not.
- Cultural dilemmas should be denied to not allow them to disrupt project work.
- Communicating across cultures should only be done using language. The nonverbal dimension bears too many risks.
Answer: A
- What are dummy activities?
- Activities in PDM which are not necessary and can be dropped if time is running out.
- Arrows in ADM which represent dependencies between nodes without real activities.
- Activities, which can be passed to the team members with the lowest IQ.
- Activities in PDM which are not performed by team members.
Answer: B
« Previous || Next »
PMP Sample Question Number :
1-10|
11-20|
21-30|
31-40|
41-50|
51-60|
61-70|
71-80|
81-90|
91-100|
101-110|
111-120|
121-130|
131-140|
141-150|
151-160
|
|