- A project manager performs Earned Value Analysis and finds the following values:
EV: 100,000; PV: 125,000; AC: 100,000
- The project is on schedule but costs exceed budget.
- The project is on schedule and on budget.
- The project is behind schedule but on budget.
- Then project is behind schedule and costs exceed budget.
Answer: C
- What are "Global Literacies"?.
- The ability to read reports written in many different languages.
- The ability to succeed in a cross cultural environment.
- The ability to develop internationally accepted contracts.
- The ability to communicate using drawings and pictograms which are understood all over the world
Answer: B
- During a project the scope of product purchased on a cost reimbursable contract has increased. In the contract the contractor‘s indirect costs are calculated as 20 % of the direct costs. What is most likely to be true?
- The contractor‘s indirect costs will increase and the customer‘s payment for them will increase, too.
- The contractor‘s indirect costs will increase but the customer‘s payment for them not.
- Neither the indirect costs nor the customer‘s payment for indirect costs will increase.
- The contractor‘s indirect costs will not increase but the customer‘s payment for them will.
Answer: D
- A project management team is evaluating the causes that might contribute to unsatisfactory performance and quality. Which of the following statements is not true?
- Normal process variation is attributable to random causes.
- Special causes are easier to predict and handle than random causes.
- Special causes are unusual events.
- A process can be optimized to limit the bandwidth of variations due to random causes.
Answer: B
- You are performing a project management audit in your company and find that most of the project plans are neither consistent nor up-to-date.
Which of the following statements is not true?
- Projects should never be executed without a valid, updated and working project plan.
- The project plan is secondary because it is only the results that matter.
- A great deal of effort is required to develop and update a project plan, but the benefits include less pressure on all stakeholders and a resulting product that will satisfy the requirements.
- Poor planning is one of the major reasons for cost and time overruns.
Answer: B
- What is active risk acceptance?
- Creating contingency reserves in money and time.
- Developing a plan to minimize potential impact.
- Developing a plan to minimize probability.
- Making additional resources available
Answer: A
- Project costs are over budget when
- CPI > 1.
- CPI < 1.
- CPI < 0.
- SPI = 1.
Answer: B
- Which of the following statements is not true?
- Only those who realize that cultural differences are a resource to be fully utilized will survive.
- There is a common ground for people from different cultures on which they can interact without unsolvable conflicts.
- Cultural differences will always be an obstacle to be overcome.
- Culture is a critical lever for competitive advantage.
Answer: C
- What is a quality audit?
- A team meeting dedicated to measuring and examinations.
- A quality based inspection of work results.
- A structured review of quality management activities.
- A meeting with the customer to identify quality requirements.
Answer: C
- You are assigned as the project manager in a project with an aggressive schedule. During a recent meeting your team complained about the high pressure applied and the many hours of overwork time.
What is the preferred solution to handle the problem?
- Try to obtain additional budget and time.
- Improve team communication and availability of high quality data on risks. Use this information to enable you to make well-founded decisions earlier.
- The problem might be the customer disturbing project rhythm. Keep him on distance from the team.
- Apply fast tracking to shorten project duration without additional work.
Answer: A
« Previous || Next »
PMP Sample Question Number :
1-10|
11-20|
21-30|
31-40|
41-50|
51-60|
61-70|
71-80|
81-90|
91-100|
101-110|
111-120|
121-130|
131-140|
141-150|
151-160
|
|